Planned activity for September 12 - 25
• Raulston Road at Carpenters Grade remains closed with traffic being detoured to relocated Cochran Road.
• Curbing work on Raulston Road is expected to continue Monday, Sept. 15 with asphalt paving to follow before the road is opened.
• Removal of old electrical poles will begin soon.
• Relocation work for gas, phone lines, and cable is nearing completion.
• Raulston Road will be re-opened to traffic when paving is complete. Cochran Road will be closed temporarily following the opening of Raulston.
• Police presence continues.
Important Note:
• When Phase III begins, northbound Carpenters Grade traffic will use Cochran Road. Southbound Carpenters Grade will remain open.
We appreciate your support while we work to improve your roads.
For more information visit our website at: www.maryvillegov.com/carpenters.html
Please Remember:
Large equipment and workers may be present throughout the day. We ask that all drivers please slow down, use extra caution, and be patient when traveling through the work zone and on Cochran Road. Drivers may encounter delays, please plan accordingly. Police Officers are present and working to reduce speeding and careless driving.