Planned Activity:
- On Friday, November 7, contractors will be paving the multi-use path.
- On Monday, November 10, Cochran Road will be paved (weather permitting).
- New all-way stop signs are expected to be installed early on Wednesday, November 12th.
- Cochran Road is expected to open to traffic mid-day Wednesday. November 12 th.
- Once Cochran Road opens, Phase III of the Traffic Control Plan will begin.
- Utility relocation work is nearing completion.
New Traffic Pattern Expected November 12, 2025
When Phase III begins, the intersection of Cochran Road and Raulston Road will become an all-way stop to accommodate detoured eastbound traffic from Carpenters Grade Road.
This temporary all-way stop will remain in place for approximately 6–8 months, until Phase III is complete.
Important Traffic Notes During Phase III:
· Northbound Carpenters Grade traffic will be detoured to Cochran Road.
· Southbound Carpenters Grade Road will remain open with traffic moving onto the multi-use path between Melrose Station and Barrington.
· Residents exiting Cross Creek, Oxford Hills, and Knightsbridge subdivisions will be right turn only onto Carpenters Grade Road.
· Residents exiting the Villas at Carpenters Grade, Legacy Court, and Kirkland Estates subdivisions will be left turn only.
· The temporary traffic signal on Carpenters Grade Road at Cross Creek Drive will provide improved access for internal subdivision traffic to enter Carpenters Grade Road.
Safety Reminder
Large equipment and workers will be present throughout the day.
Please:
- Slow down and use extra caution in the work zone and on Cochran Road.
- Expect delays and plan extra travel time.
- Follow police directions—officers are on site to help reduce speeding and unsafe driving.
We appreciate your support while we work to improve your roads.
For more information visit our website at: www.maryvillegov.com/carpenters.html